Main Outfall Relief Sewer

City of Akron

$1,400,000

The focus of this project was to increase the capacity of the Main Outfall Relief Sewer in Akron, Ohio by removing the top of the brick sewer and replacing it with a precast concrete top. The major items of work included demolition, drilling augercast piling, pouring a new foundation and sidewalls and then installing a precast concrete top.