Easterly WWTP Final Clarifier Rehabilitation

Northeast Ohio Regional Sewer District

$2,375,000

The Easterly Final Clarifier Rehabilitation project called for the removal of the mechanical drive units and installation of new mechanical drive units at final clarifier nos. 4, 5, 7, And 10. The work also included the complete removal of existing coating systems and application of new coating systems from the walkway bridges, the center influent columns and the sludge raking mechanisms at final clarifiers. Kenmore crews also replaced six water valves and operators and thirty-two motor actuators to the existing influent sluice gate floor stands in the aeration tanks.